Land Acquisition Compensation in Uttar Pradesh: Reference, Appeal and Writ Remedies in the Allahabad High Court

By Advocate Arvind TripathiNovember 15, 202615 min read
Featured illustration for Land Acquisition Compensation in Uttar Pradesh: Reference, Appeal and Writ Remedies in the Allahabad High Court
When land in Uttar Pradesh is acquired and the award is too low, the remedy depends on the law under which the land was taken. This article explains the reference under Section 64 of the 2013 Act and its six-week limit, the separate arbitration route for national highway land, the sixty-day appeal to the High Court, and the situations in which a writ petition is the proper course, on the law as it stands on 15 November 2026.

Practice area: All practice areas of Shri Law Chambers

On 16 October 2026 the Supreme Court held that an appeal to the High Court against a land acquisition award cannot be heard if it is filed even one day after the 120th day (Rajasthan Housing Board v. Hariyali Rural Ventures Ltd., 2026 INSC 1168). Eight months earlier, on 9 February 2026, another Bench of the same Court had held that such delay can be excused. For an owner in Uttar Pradesh whose field has gone into a road, an industrial area or a housing scheme, the lesson is uncomfortable. He can be right about the price of his land and still lose because a paper was late.

This article is about compensation for acquired land in Uttar Pradesh, on the law as it stands on 15 November 2026. It makes two points. First, the route to a higher amount depends on the law under which the land was taken, not on the size of the project. Land taken under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (the 2013 Act) goes by a "reference" to a special Authority and then by appeal to the High Court. Land taken for a national highway goes to an arbitrator and reaches the High Court only at the third stage. Second, the Allahabad High Court's part is narrower than most owners expect when the complaint is about the rate, and wider than they expect when the complaint is that the State has not followed the law at all. Time limits join the two points: the shortest ones belong to the first route, and they start on the date of the award.

Which law took the land

The notice or award in the owner's hand answers this, and three situations are common in Uttar Pradesh.

The first is acquisition under the 2013 Act, in force from 1 January 2014 and used for most State projects. The Collector makes the award; in practice this is often a Special Land Acquisition Officer or an Additional District Magistrate exercising the Collector's powers.

The second is acquisition for a national highway under the National Highways Act, 1956. Here there is no Collector's award. An officer called the competent authority fixes the amount under Section 3G(1).

The third is not an acquisition at all: land bought by a registered sale deed under the State's procedure for purchase by mutual agreement (Government Order of 19 March 2015), or land simply used for a road or a canal without any order. A sale by agreement produces no award, so the remedies below that begin with an award do not fit it in the same way. Land used without any order is dealt with further down.

Older cases need one more check. Where proceedings began under the Land Acquisition Act, 1894 but no award had been made by 1 January 2014, Section 24(1)(a) of the 2013 Act applies the new Act's compensation provisions. In Chandrabhan Yadav v. State of U.P. (Writ-C No. 18397 of 2018, decided 10 January 2024, 2024:AHC:5253-DB), possession had been taken in 2012 and the award came on 26 December 2014. A Division Bench of the Allahabad High Court held, at paragraph 9, that compensation had to be worked out under the 2013 Act whatever the date of possession. The opposite claim, that an old acquisition has "lapsed" under Section 24(2) because compensation was not paid, is now hard to make. A Constitution Bench held in Indore Development Authority v. Manoharlal (2020) 8 SCC 129, decided on 6 March 2020, that there is a lapse only where the authorities have neither taken possession nor paid.

What the award must add up to

Under the 2013 Act compensation is built in steps, and an award can be checked against each of them.

• Market value under Section 26: the higher of the circle rate fixed for stamp duty and the average sale price of similar land in the village or its vicinity. The average is taken from sale deeds of the preceding three years, counting only the half with the highest prices. The date that matters is the date of the preliminary notification under Section 11.

• The multiplying factor in the First Schedule: 1 in urban areas, and between 1 and 2 in rural areas according to distance from the urban area, as notified by the State. Uttar Pradesh has issued notifications on this factor (22 October 2014 and 13 July 2016), and the one in force on the relevant date has to be read with the award. This article does not state a figure because the current text could not be checked against an official copy.

• The value of trees, buildings, wells and standing crops (Sections 27 and 29).

• Solatium equal to one hundred per cent of the compensation (Section 30(1)).

• An additional amount at twelve per cent a year on the market value, from the notification of the social impact study to the award or the taking of possession, whichever is earlier (Section 30(3)).

Most disputes are about the first step: which sale deeds were used, whether land beside a road or the village abadi was valued as ordinary farm land, and whether the right circle rate was applied. Those are questions of evidence, and that decides where they have to be raised.

The reference: six weeks, and two words on the receipt

An owner who does not accept the Collector's award can require, by a written application to the Collector, that the matter be referred to the Land Acquisition, Rehabilitation and Resettlement Authority (Section 64). The application can question the measurement of the land, the amount, the persons to whom it is payable, rehabilitation entitlements, or the division of the money among co-owners. It must state the grounds.

The time is short. If the owner or his representative was present when the award was made, he has six weeks from the award. Otherwise he has six weeks from the Collector's notice under Section 21, or six months from the award, whichever ends first. The Collector may accept a late application within one further year for sufficient cause. That is a discretion, not a right.

A second trap sits in Section 77. The owner may receive the awarded amount "under protest as to the sufficiency of the amount", and a person who has received it otherwise than under protest is not entitled to apply under Section 64. The protest should be in writing, on the receipt itself or in a dated letter given at the same time. It is safer to record it than to argue later that it was implied.

The Collector must make the reference within thirty days. If he does not, the owner may apply to the Authority for a direction to him. In Uttar Pradesh the Authority, usually called LARRA, sits at several centres, among them Prayagraj, Lucknow, Jhansi and Basti, and judicial officers are posted as its Presiding Officers.

Before the Authority the owner stands like a plaintiff. He must prove the higher value with sale deeds, circle rate lists, maps and, where needed, a valuer's report. The Authority can confirm the Collector's figure or raise it. It cannot send the matter back to the Collector to begin again. In State of U.P. v. Iftekhar Ahmad (First Appeal No. 387 of 2026, decided 10 April 2026), Justice Sandeep Jain set aside an order of the Authority at Basti that had cancelled the Collector's award and remanded the matter, holding that a reference is an original proceeding and carries no power of remand (paragraphs 8, 12 and 13). Where the Authority awards more, it adds twelve per cent a year on the market value from the preliminary notification (Section 69(2)), and it may direct interest on the excess at nine per cent for the first year after possession and fifteen per cent after that (Section 72).

One provision helps neighbours. If the Authority raises the compensation for one owner, others whose land was covered by the same preliminary notification may apply to the Collector within three months of the Authority's award for the same rate, even though they sought no reference themselves (Section 73).

Highway land: a different route

Run the same dispute through the National Highways Act and almost every step changes. The competent authority fixes the amount. An owner who does not accept it applies for determination by an arbitrator appointed by the Central Government (Section 3G(5)); in practice the arbitrator is usually the Collector or the Commissioner. The Arbitration and Conciliation Act, 1996 then applies (Section 3G(6)). The arbitrator's award can be challenged before the District Judge under Section 34 of that Act within three months, extendable by thirty days and no more, and the District Judge's decision can be appealed to the High Court under Section 37.

The weakness of this route is its later stages. A court hearing a Section 34 petition does not hear the valuation afresh. In Project Director, NHAI v. M. Hakeem (2021) 9 SCC 1, the Supreme Court held that the power to set aside an award does not include a power to modify it. A Constitution Bench in Gayatri Balasamy v. ISG Novasoft Technologies Ltd., 2025 INSC 605, decided on 30 April 2025, has since allowed modification, but only in limited situations such as a severable part of the award, clerical or calculation errors and post-award interest. So the evidence of value has to be complete before the arbitrator. What is not proved there can rarely be added later.

Solatium and interest were for years refused to highway landowners, because Section 3J shut out the general acquisition law. The Supreme Court held that exclusion unconstitutional in Union of India v. Tarsem Singh (2019) 9 SCC 304. On 25 March 2026, in National Highways Authority of India v. Tarsem Singh, 2026 INSC 291, it declined to go back on that position but drew a line at 28 March 2008. Owners whose claims were pending before some forum on or after that date can ask for solatium and interest to be added. Those who asked late get no interest for the period of delay. Cases that had ended before that date cannot be reopened, and nothing already paid can be recovered (paragraphs 14 and 17).

Which Act supplies the rates depends on the date of the competent authority's order. If it was made before 1 January 2015, solatium and interest are worked out under the 1894 Act, even where the arbitrator decided later; if on or after that date, under the 2013 Act. That is the ruling in Manav Bhanot v. National Highway Authority of India, decided on 8 September 2026 (2026 LiveLaw (SC) 915, paragraphs 13, 19 and 24).

A quarrel among co-owners over shares is handled differently again. Under Section 3H(4) the competent authority must send it to the principal civil court. In Mohd. Yaseen v. Mohd. Asif (2026 LiveLaw (AB) 493, reported on 30 July 2026), a Division Bench of the Allahabad High Court directed the Additional District Magistrate, Bulandshahr to make that reference after he had divided the money between two branches of a family himself.

The arbitration route is itself under examination. In M/s Riar Builders Pvt. Ltd. v. Union of India, the Supreme Court on 13 January 2026 asked the Union to look again at Sections 3G and 3J, and at the hearing of 23 July 2026 the Chief Justice described the decision of these disputes by administrative officers as "prima facie not acceptable". The Attorney General told the Court that an amendment was under consideration. No amendment had been reported when this article was written, and pending arbitrations continue.

"Why not a writ petition?"

Many owners ask why all of this cannot be avoided by a writ petition under Article 226 of the Constitution. The question is fair. Section 63 of the 2013 Act bars civil courts, not the High Court's writ jurisdiction, and the High Court is the court most owners would rather be in.

The State's answer is that the Act gives its own remedy, and on the rate of compensation that answer usually succeeds. Fixing market value needs evidence, and a writ court does not ordinarily take evidence. Chandrabhan Yadav shows both halves. In his first writ petition the High Court did not disturb the award and left him to seek a reference. He applied, and the Collector refused, saying that the old Act governed. His second writ petition succeeded: the refusal was quashed and the Collector was directed to make the reference within three weeks (paragraphs 10 to 12). The High Court would not decide the price. It would make the officer do what the statute required.

That is the pattern. A writ petition is the proper course in four kinds of case.

• Land used without any acquisition. In Kanyawati v. State of U.P. (2025:AHC:29933-DB, decided 4 March 2025), part of a holding in Bareilly had gone into a widened road. A Division Bench held the owner entitled to compensation under Article 300A of the Constitution and directed the District Level Committee to determine and pay it within four weeks, with interest under the 2013 Act. The Supreme Court had held in Vidya Devi v. State of Himachal Pradesh (2020) 2 SCC 569 that the State cannot defeat such a claim by pleading delay or adverse possession. Uttar Pradesh has a procedure for these claims in Government Order No. 327 of 12 May 2016.

• A Collector who refuses or delays a reference, or applies the wrong Act, as in Chandrabhan Yadav.

• An award of the Authority that has become final and is still not paid (see the next section).

• A challenge to the acquisition itself for breach of procedure. This has to be brought early, and the Court looks at whether each statutory step was followed. On 28 April 2026 the High Court upheld the acquisition for the expansion of the Noida International Airport on that footing (Vijay Pal Singh v. State of U.P., Writ-C No. 41339 of 2025).

The appeal, the 120 days, and getting paid

An award of the Authority can be appealed to the High Court under Section 74, by the owner or by the body for which the land was acquired. At Allahabad it is registered as a First Appeal. The period is sixty days from the award, and the High Court may allow a further sixty days for sufficient cause.

What happens after the 120th day is where this article began. In Deputy Commissioner and Special Land Acquisition Officer v. S.V. Global Mill Ltd., 2026 INSC 138, decided on 9 February 2026, Justices M.M. Sundresh and Satish Chandra Sharma held that Section 74 does not exclude Section 5 of the Limitation Act, 1963, so that the High Court can condone longer delay. In Hariyali, Justices Dipankar Datta and Sheel Nagu read the section the other way. The 120 days are "inflexible and rigid", Section 5 does not apply, and the Bench declined to refer the question to a larger Bench (paragraphs 17, 20 and 21).

Both are decisions of two Judges. Hariyali did not arise from a late appeal: the Housing Board had gone to its High Court under Article 227 instead of appealing, and the order itself says that S.V. Global Mill would not have applied to those facts (paragraph 23). It also leaves pending time-barred appeals to be decided by the High Courts in accordance with law (paragraph 24). That gives an owner whose appeal is already late something to argue. An owner whose time is still running should not plan on that argument. Until a larger Bench settles the point, the working rule is sixty days.

Winning before the Authority is not the same as being paid. On 28 September 2026, in Lucknow Development Authority v. Ramrati (Matters under Article 227 No. 143 of 2026, with 44 connected petitions), Justice Jaspreet Singh, sitting at Lucknow, held that the Authority has no power to execute its own award (paragraphs 237 and 252). The award has the force of a decree and is executed by the District Judge, who cannot reopen its merits (paragraphs 238 to 242). Where an award is final and the department still delays payment, the owner may come to the High Court by writ petition (paragraphs 246 to 250). The Court suggested that the State give the Authority execution powers by rules (paragraph 251). Until that is done, execution lies in the District Court.

What to keep ready

• The award, or the competent authority's order, with the date it was made and the date and manner in which notice of it was received.

• The notifications: the preliminary notification under Section 11 and the declaration under Section 19 of the 2013 Act, or the notifications under Sections 3A and 3D of the National Highways Act.

• The khatauni and khasra for the plot, and a map showing where it lies in relation to roads and the abadi.

• Certified copies of sale deeds of similar land in the village and neighbouring villages for the three years before the notification, and the circle rate lists for those years.

• The receipt for any amount received, and the written protest.

• Photographs, and any valuation, of trees, borewells, boundary walls and buildings.

• For land used without acquisition: revenue records showing title, and any tehsil or inspection report showing that the land lies within the road or project.

Conclusion

Go back to the owner who is right about the price. Under the 2013 Act the law gives him an Authority that hears evidence, an appeal to the High Court, and interest of up to fifteen per cent a year on what was withheld. It also gives him six weeks to begin and sixty days to appeal, and it expects him to write "under protest" before he signs for the money. Under the National Highways Act he has one full hearing on value, before an officer, and a narrow review after it.

Two things are unsettled. One is whether a larger Bench of the Supreme Court will resolve the difference between S.V. Global Mill and Hariyali on late appeals. The other is whether Parliament will replace the arbitrator under Section 3G(5) with a judicial forum, as the Supreme Court asked in July 2026. Neither changes what an owner holding a fresh award has to do this month.

Key Authorities Cited

  • Rajasthan Housing Board v. Hariyali Rural Ventures Ltd.Supreme Court of India, 2026-10-162026 INSC 1168; SLP (C) No. 35141 of 2026Paras: 17, 20, 21, 23, 24
  • Deputy Commissioner and Special Land Acquisition Officer v. S.V. Global Mill Ltd.Supreme Court of India, 2026-02-092026 INSC 138; 2026 LiveLaw (SC) 130
  • State of U.P. v. Iftekhar AhmadAllahabad High Court, 2026-04-10First Appeal No. 387 of 2026Paras: 8, 12, 13
  • Lucknow Development Authority v. RamratiAllahabad High Court (Lucknow Bench), 2026-09-28Matters under Article 227 No. 143 of 2026Paras: 237, 238, 239, 240, 242, 246, 250, 251, 252
  • Chandrabhan Yadav v. State of U.P.Allahabad High Court, 2024-01-102024:AHC:5253-DB; Writ-C No. 18397 of 2018Paras: 9, 10, 11, 12
  • Kanyawati v. State of U.P.Allahabad High Court, 2025-03-042025:AHC:29933-DB
  • Vijay Pal Singh v. State of U.P.Allahabad High Court, 2026-04-28Writ-C No. 41339 of 2025
  • Mohd. Yaseen v. Mohd. AsifAllahabad High Court2026 LiveLaw (AB) 493
  • Union of India v. Tarsem SinghSupreme Court of India, 2019-09-19(2019) 9 SCC 304
  • National Highways Authority of India v. Tarsem SinghSupreme Court of India, 2026-03-252026 INSC 291; 2026 LiveLaw (SC) 293Paras: 14, 17
  • Manav Bhanot v. National Highway Authority of IndiaSupreme Court of India, 2026-09-082026 LiveLaw (SC) 915Paras: 13, 19, 24
  • Project Director, National Highways Authority of India v. M. HakeemSupreme Court of India, 2021-07-20(2021) 9 SCC 1
  • Gayatri Balasamy v. ISG Novasoft Technologies Ltd.Supreme Court of India (Constitution Bench), 2025-04-302025 INSC 605
  • M/s Riar Builders Pvt. Ltd. v. Union of IndiaSupreme Court of India, 2026-01-13SLP (C) Diary No. 26933 of 2025; 2026 LiveLaw (SC) 65
  • Indore Development Authority v. ManoharlalSupreme Court of India (Constitution Bench), 2020-03-06(2020) 8 SCC 129
  • Vidya Devi v. State of Himachal PradeshSupreme Court of India, 2020-01-08(2020) 2 SCC 569

Statutory Provisions

  • Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - Section 24(1)(a) and (2) (pending proceedings under the 1894 Act; lapse)
  • Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - Sections 26 to 30 and the First Schedule (market value, multiplying factor, assets, solatium, additional twelve per cent)
  • Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - Section 63 (bar on civil courts) and Section 64 (reference to the Authority; time limits)
  • Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - Sections 69, 72 and 73 (award of the Authority; interest on excess; re-determination for other owners)
  • Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - Section 74 (appeal to the High Court within sixty days, extendable by sixty days)
  • Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - Section 77 (payment; receipt under protest)
  • National Highways Act, 1956 - Sections 3G(1), 3G(5), 3G(6), 3H(4) and 3J (competent authority's determination; arbitrator; application of the Arbitration Act; apportionment disputes)
  • Arbitration and Conciliation Act, 1996 - Sections 34 and 37 (setting aside an arbitral award; appeal)
  • Limitation Act, 1963 - Section 5 (extension of the prescribed period)
  • Constitution of India - Articles 226, 227 and 300A

Frequently Asked Questions

The Collector's award gives far less than what land sells for in my village. What can I do?

Under the 2013 Act, apply in writing to the Collector for a reference to the Land Acquisition, Rehabilitation and Resettlement Authority under Section 64, stating your grounds. If you were present or represented when the award was made, you have six weeks from the award; otherwise six weeks from the Collector's notice or six months from the award, whichever ends first. Before the Authority you will need sale deeds of similar land and the circle rate lists to prove the higher value.

I have already taken the compensation. Is it too late to ask for more?

It depends on how you took it. Section 77 of the 2013 Act allows the amount to be received under protest as to its sufficiency, and says that a person who received it otherwise than under protest cannot apply for a reference under Section 64. Look at the receipt and at any letter you gave at the time, and check the dates against the six-week period.

My land was taken for a national highway. Is the procedure the same?

No. The amount is fixed by the competent authority under Section 3G(1) of the National Highways Act, 1956. If you do not accept it, you apply for determination by an arbitrator appointed by the Central Government under Section 3G(5). The arbitrator's award can be challenged before the District Judge under Section 34 of the Arbitration and Conciliation Act, 1996, and then in appeal to the High Court under Section 37. The court does not value the land afresh at those stages, so the evidence has to be placed before the arbitrator.

A road was built over part of my field years ago. Nobody acquired the land or paid for it. Do I still have a remedy?

A writ petition in the High Court is the remedy. In Kanyawati v. State of U.P. (4 March 2025) the Allahabad High Court directed that compensation be determined and paid for land used in road widening without acquisition, and the Supreme Court held in Vidya Devi v. State of Himachal Pradesh (2020) that the State cannot rely on delay or adverse possession to keep such land without paying. You will need revenue records showing your title and proof that the land lies within the road.

How long do I have to appeal to the High Court against the Authority's award?

Sixty days from the award under Section 74, and the High Court may allow up to sixty more for sufficient cause. Whether anything later than 120 days can be excused is disputed between two Supreme Court decisions of 2026, S.V. Global Mill (February) and Hariyali (October). Treat sixty days as the limit.

The Authority raised my compensation last year, but the department has still not paid. Whom do I approach?

Not the Authority. In Lucknow Development Authority v. Ramrati (28 September 2026) the High Court held that the Authority cannot execute its own award. The award is executed like a decree by the District Judge, and if payment of a final award is still delayed, a writ petition can be filed in the High Court.

My brothers and I do not agree on our shares in the compensation. Who decides?

Under the 2013 Act a dispute about the division of compensation can be referred to the Authority under Section 64. For national highway land, Section 3H(4) requires the competent authority to refer the dispute to the principal civil court, and the Allahabad High Court applied this in Mohd. Yaseen v. Mohd. Asif (2026). For highway land, the officer distributing the money cannot decide a contested share himself.

Sources & References

Advocate Arvind Kumar Tripathi
About the AuthorArvind Kumar Tripathi, Advocate

Shri Law Chambers. Practises before the Allahabad High Court in service and criminal matters; in practice since 1991.

Enrolled with the Bar Council of Uttar Pradesh, 1991 · Advocate-on-Record, Allahabad High Court · Allahabad High Court Bar Association · LL.B., Faculty of Law, University of Allahabad, 1990 · Former standing counsel: Government of India; Zila Panchayat, Kanpur Nagar; Fisheries Department (Matsya Palan Vibhag), Government of Uttar Pradesh