Land Acquisition in Uttar Pradesh: The Questions Landowners Ask Most

Practice area: All practice areas of Shri Law Chambers
In the first week of October 2026, farmers from 55 villages of Sadar tehsil in Mirzapur were called to a meeting of the purchase committee formed by the District Magistrate for the Vindhya Expressway. They were told, as Amar Ujala reported, that land would be paid for at four times the circle rate in rural areas and twice the circle rate in urban areas. Six weeks earlier, in August 2026, a Division Bench of the Allahabad High Court at Lucknow had heard landowners from Balrampur who said they were being pressed to sign sale deeds for a road at a price they did not accept. The Bench, as The Pioneer reported, held that land can be bought by sale deed only from an owner who agrees to sell at a price both sides accept. Without that consent, the State must acquire the land under the statute.
Those two events contain most of the questions that owners in Uttar Pradesh bring to a lawyer when a project comes near their land. This article answers them in the order in which they usually arise, on the law as it stands on 15 November 2026. It makes two points. First, in Uttar Pradesh the decisive choice is often made before any award: whether to sign the sale deed offered by the purchase committee or to wait for compulsory acquisition under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (the 2013 Act). Second, the protections that owners hear about (no possession before payment, interest for delay, the return of unused land, freedom from income tax) are written for compulsory acquisition. Some of them apply differently, or not at all, once the land has been sold by agreement.
What to do when an award has already been made and the amount is too low (the reference to the Authority, the appeal to the High Court and the writ petition) is discussed separately in this series, in "Land Acquisition Compensation in Uttar Pradesh: Reference, Appeal and Writ Remedies in the Allahabad High Court".
Before the award
"Can the government take my land if I refuse to sell?"
For a public purpose, yes. The 2013 Act does not require the owner's consent when the land is acquired for the Government's own project. Consent is required in two situations only, both under Section 2(2): where the land is acquired for a private company, the prior consent of at least eighty per cent of the affected families; and for a public-private partnership project, at least seventy per cent.
What the State cannot do is treat an owner who refuses to sell as if he had agreed. A sale deed is a contract. If the owner does not sign, the State's route is a notification under the 2013 Act, with its social impact study, hearing of objections, declaration and award. That is the position the High Court stated in the Balrampur case reported in August 2026, and the Bench directed the authorities not to harass the petitioners or obtain their consent by pressure. An owner who refuses does not stop the project. He changes the route by which the price will be fixed.
"When can I object, and what can I object to?"
There are two occasions. The first is the public hearing held during the social impact assessment, before any notification of acquisition. The second is formal: under Section 15, any person interested in land notified under Section 11 (the preliminary notification) may file objections with the Collector within sixty days of its publication.
The grounds are limited. Section 15(1) allows objections to the area and suitability of the land proposed, to the justification offered for the public purpose, and to the findings of the social impact assessment report. The Collector hears the objections and reports to the State Government, whose decision on them is final under Section 15(3).
The price is not decided at this stage. An owner who uses his sixty days only to say that the rate will be low has used them on the wrong question. The rate is fixed in the award, and a dispute about it goes by reference to the Authority after the award. Objections are the place to say that the land is not needed, that less land would do, that a house or a well could be left out by a change of alignment, or that the social impact report has missed families who live off the land.
The money
"Is it really four times the circle rate?"
Sometimes, and the reason it is sometimes and not always lies in the arithmetic of the 2013 Act.
• Market value: under Section 26 it is the higher of the circle rate fixed for stamp duty and the average price of similar land in the vicinity, taken from the highest-priced half of the sale deeds of the preceding three years.
• The multiplying factor: under the First Schedule the market value is multiplied by 1 in urban areas, and by a factor between 1 and 2 in rural areas according to distance from the urban area, as notified by the State.
• Solatium: one hundred per cent of the compensation so worked out is added under Section 30(1).
Take rural land whose market value comes to ₹10 lakh a bigha, at a distance for which the notified factor is 2. The land component becomes ₹20 lakh; solatium adds another ₹20 lakh; the owner receives ₹40 lakh, four times the market value, before the value of trees, wells and buildings and the additional twelve per cent a year under Section 30(3) are added. In an urban area, with a factor of 1, the same arithmetic gives two times.
So "four times the circle rate" is true only if two things are true at once: the circle rate is the market value (that is, the sale deeds of the village show no higher price), and the factor notified for that distance is 2. Where good sale deeds exist, the market value can exceed the circle rate. Where the land is nearer a town, the factor may be less than 2. Uttar Pradesh has issued notifications on the factor, and the one in force on the relevant date has to be read with the award; this article does not state a figure because the current text could not be checked against an official copy.
The "four times" heard at purchase committee meetings, as in Mirzapur, is something different. It is the rate offered for buying the land by agreement, worked out on the circle rate. It is a price, not a computation under Section 26, and it does not grow if the village's sale deeds turn out to be better than the circle rate.
"Should I sign the sale deed or wait for the award?"
This is the question on which most of the rest depends, and the honest answer is that it cuts both ways.
The case for signing is real. The purchase is quicker, the money comes in one payment, and in rural areas the rate offered in Uttar Pradesh has for years been four times the circle rate, which is what the Act's own arithmetic gives where the factor is 2 and the circle rate is the market value. An owner who waits may receive an award at the same figure, a year or more later, after a social impact study, a notification and an enquiry. For a small holding, the cost and delay of disputing a few lakh rupees can exceed the gain.
The case against signing is that a sale deed is final in a way an award is not. In Ramveer Singh v. State of U.P. (Writ-C No. 15071 of 2025, decided 3 July 2025, 2025:AHC:103454-DB), the owner had sold his land by registered sale deed in February 2015 and later asked the High Court for a higher amount. A Division Bench dismissed the writ petition, holding at paragraph 7 that a claim for any sale consideration higher than that stated in the sale deed is not tenable in law. Ordinarily there is no reference to the Authority from a sale deed, no appeal under Section 74, and no claim under Section 73 when a neighbour's compensation is later raised. An owner who has a strong case on value, for example land on a road frontage, land next to the abadi, or recent high-value sale deeds in the village, gives up the forum in which that case would have been heard.
The sale deed has a second risk: payment. In August 2026 the High Court at Lucknow heard a temple whose land at Sugriv Kila in Ayodhya had been taken under a registered sale deed of 22 December 2023 for development works, while the land price of about ₹1.20 crore remained unpaid. The Bench directed the State to deposit the amount with interest at eight per cent a year (Shri Thakur Ram Janki Sugrivji Virajman Mandir v. State of U.P., Writ-C No. 4372 of 2026, 2026:AHC-LKO:55848-DB). The temple got its order, but only by a writ petition, because Section 38 of the 2013 Act (no possession before payment) governs acquisition, not a sale.
The practical rule that follows: sign only if the rate is one you would accept as final, and register the sale deed only against payment or a verified deposit. If the rate is wrong, do not sign, and keep the evidence of value ready for the award.
"Will I pay income tax on the money?"
For compulsory acquisition under the 2013 Act, ordinarily no. Section 96 of the Act says that no income tax or stamp duty is to be levied on an award or agreement made under the Act, except one made under Section 46 (purchase by a private person). The Central Board of Direct Taxes accepted this in Circular No. 36 of 2016, dated 25 October 2016. The Finance Act, 2026 has now written it into the Income-tax Act, 2025: Section 123 of the Finance Act inserted serial number 38C in Schedule III, which exempts any income of an individual or a Hindu undivided family in respect of an award or agreement made on account of compulsory acquisition of land under the 2013 Act, other than under Section 46.
Three limits should be kept in view. The new entry speaks of individuals and Hindu undivided families; a company or firm whose land is acquired has to rely on Section 96 itself. Land taken under another statute, such as the National Highways Act, 1956, raises a separate question that has been argued before tax tribunals. And whether a sale deed signed under the State's purchase policy is an "agreement made under" the 2013 Act is a question on which this article does not express a view. An owner choosing the sale-deed route should take the advice of a chartered accountant on the tax position before he signs, not after.
"Who in the family gets the money?"
The Collector pays the persons interested, which in practice means those recorded in the khatauni. If the recorded owner has died and the heirs' names have not been entered, the payment will wait for that entry. Getting the names recorded by succession (varasat) before the award is one of the most useful steps a family can take.
Where the family does not agree on shares, Section 77(2) requires the Collector to deposit the money with the Authority instead of choosing between claimants, and the dispute about division can be taken to the Authority by reference under Section 64. For national highway land the procedure is different, and is described in the first article in this series.
"We work on the land but do not own it. Do we get anything?"
Possibly. The 2013 Act separates compensation for the land, which goes to the owners, from rehabilitation and resettlement, which goes to every "affected family". Under Section 3(c) that includes families who do not own land but whose members have worked on it as agricultural labourers, tenants or sharecroppers for three years before the acquisition, and whose primary livelihood is affected.
The Second Schedule sets the minimum entitlements. Each affected family is to be offered a choice of employment where the project creates jobs, a one-time payment of ₹5 lakh, or an annuity of not less than ₹2,000 a month for twenty years, indexed to the consumer price index for agricultural labourers. A family displaced from its home receives, among other things, a subsistence allowance of ₹3,000 a month for one year. Under Section 31 the Collector passes a separate rehabilitation and resettlement award for each affected family. A purchase by sale deed is a transaction with the owner; whether a particular purchase scheme provides anything to the families who worked the land depends on its own terms.
After the award
"Can they take the land before paying?"
Under the 2013 Act, no. Section 38(1) allows the Collector to take possession only after ensuring that full compensation, and the rehabilitation and resettlement entitlements, have been paid or tendered: within three months of the award for compensation, and within six months for the money part of the rehabilitation and resettlement entitlements. In M/s Ultra-Tech Cement Ltd. v. Mast Ram (2024 INSC 709, decided 20 September 2024), the Supreme Court read the section in exactly that way: payment of full and final compensation is the precondition for taking possession.
The exception is urgency. Under Section 40 the State may take possession early in limited cases, such as defence, national security or a natural calamity. Before doing so the Collector must tender eighty per cent of the estimated compensation, and Section 40(5) adds an extra seventy-five per cent of the total compensation, except where the project concerns the sovereignty and integrity of India or the security and strategic interests of the State.
"What if the payment is late?"
Section 80 makes delay expensive for the State. If the compensation is not paid or deposited on or before possession, the Collector must pay interest at nine per cent a year from the date of possession, rising to fifteen per cent a year on any part that remains unpaid after one year. The interest is part of the owner's statutory entitlement; it does not depend on a separate claim being proved.
"What if the land is never used?"
Section 101 provides that land acquired under the 2013 Act which remains unutilised for five years from the date possession was taken shall be returned to the original owners or their legal heirs, or to the State's land bank, in the manner the Government prescribes.
The section is narrower than it sounds. In Ultra-Tech Cement the Supreme Court held that both conditions must be met: five years from possession, and the land actually lying unutilised. Land acquired as a safety zone around a cement plant, and serving that purpose, was being utilised even though nothing was built on it, and could not be returned (paragraphs 35 to 39). An owner who sees an empty field five years after the acquisition has to show that the land is not serving the purpose for which it was taken, not only that it is bare.
There is a second limit, and it brings this article back to the choice made at the start. Section 101 speaks of land "acquired under this Act". Land that the State bought by sale deed was not acquired under the Act, and it is doubtful that Section 101 reaches it. The same is true of Section 38 and Section 80, which are written for the award.
Conclusion
For an owner in Uttar Pradesh the sequence is now familiar: a purchase committee meeting, an offer at a multiple of the circle rate, and a sale deed to be signed. The law gives him the right to say no, and if he does, the State must acquire the land under the 2013 Act, which brings an award, a right of reference, possession only after payment, interest for delay and, in a narrow class of cases, the return of unused land. If he says yes, he exchanges those protections for speed and certainty, and the rate he signs for is final.
Neither choice is right for everyone. The question to ask before the meeting is not "Is it four times?" but "Four times what?", and whether the village's sale deeds, the location of the land and the family's records support a higher figure that is worth waiting for. One question remains open for owners who sell by agreement: whether the income tax exemption reaches a sale deed signed under the State's purchase policy. Until that is settled, it should be checked before the deed is signed.
Key Authorities Cited
- Ramveer Singh v. State of U.P.Allahabad High Court, 2025-07-032025:AHC:103454-DB; Writ-C No. 15071 of 2025Paras: 7
- Shri Thakur Ram Janki Sugrivji Virajman Mandir v. State of U.P.Allahabad High Court (Lucknow Bench)2026:AHC-LKO:55848-DB; Writ-C No. 4372 of 2026
- M/s Ultra-Tech Cement Ltd. v. Mast RamSupreme Court of India, 2024-09-202024 INSC 709; [2024] 9 S.C.R. 443Paras: 35, 36, 37, 38, 39
Statutory Provisions
- Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - Section 2(2) (consent for private company and public-private partnership projects)
- Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - Section 3(c) (affected family) and Section 15 (objections within sixty days of the Section 11 notification)
- Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - Sections 26 and 30 and the First Schedule (market value, multiplying factor, solatium)
- Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - Section 31 and the Second Schedule (rehabilitation and resettlement award and entitlements)
- Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - Sections 38 and 40 (possession after payment; urgency)
- Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - Sections 77(2) and 80 (deposit where shares are disputed; interest on delayed payment)
- Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - Section 96 (exemption from income tax and stamp duty) and Section 101 (return of unutilised land)
- Income-tax Act, 2025 - Schedule III, serial number 38C, inserted by Section 123 of the Finance Act, 2026
Frequently Asked Questions
The purchase committee is offering four times the circle rate. Is that what the law guarantees?
Not exactly. Under the 2013 Act, rural compensation reaches about four times the market value only where the factor notified for that distance is 2, because the market value is doubled and solatium of one hundred per cent is then added. The market value is the higher of the circle rate and the average of the better sale deeds in the vicinity, so it can be more than the circle rate. The purchase committee's four times is a price worked out on the circle rate, offered for a sale by agreement.
If I sign the sale deed, can I go to court later for a higher amount?
Ordinarily, no. In Ramveer Singh v. State of U.P. (2025) the Allahabad High Court held that a claim for consideration higher than the amount stated in the sale deed is not tenable. A sale deed is not an award, so there is no reference to the Authority and no appeal under Section 74. A deed obtained by fraud is a different matter and is challenged by a suit for cancellation.
Can officials force me to sign the bainama?
No. As reported in August 2026, the Allahabad High Court at Lucknow held that land can be bought by sale deed only from an owner who voluntarily agrees to sell at a price both sides accept, and directed the authorities not to harass the petitioners. If the owner does not agree, the State has to acquire the land under the 2013 Act.
Is land acquisition compensation taxable?
Compensation under an award or agreement made under the 2013 Act is exempt from income tax under Section 96 of that Act, except for Section 46 cases, and for individuals and Hindu undivided families the Finance Act, 2026 has added a matching entry (serial number 38C) to Schedule III of the Income-tax Act, 2025. For a sale deed signed under the State's purchase policy, or land taken under another statute, take a chartered accountant's advice before relying on the exemption.
Within how many days must objections be filed?
Sixty days from the publication of the preliminary notification under Section 11. The objections can be about the area and suitability of the land, the justification for the public purpose and the social impact assessment report; the amount of compensation is decided later, in the award.
The land was taken and the money has still not come. Do I get interest?
Under Section 80 of the 2013 Act, yes: nine per cent a year from the date of possession, and fifteen per cent a year on any amount still unpaid after one year. Section 38 also means that possession should not have been taken before payment or tender at all, except in urgency cases under Section 40.
The acquired land has been lying unused for years. Can we get it back?
Only if the conditions of Section 101 are met: the land must have remained unutilised for five years from the date possession was taken. The Supreme Court held in Ultra-Tech Cement (2024) that land serving the purpose of the acquisition, even without construction, is not unutilised. The section speaks of land acquired under the Act, so it may not help where the land was sold by sale deed.
Sources & References
- Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (India Code)
- Finance Act, 2026, Section 123: amendment of Schedule III to the Income-tax Act (Income Tax Department)
- Mirzapur: purchase committee meeting for the Vindhya Expressway, four times the circle rate in rural areas (Amar Ujala, 6 October 2026)
- Allahabad High Court: government cannot force landowners to execute sale deeds (The Pioneer, 24 August 2026)
- Ramveer Singh v. State of U.P., Writ-C No. 15071 of 2025, 3 July 2025 (LatestLaws)
- Shri Thakur Ram Janki Sugrivji Virajman Mandir v. State of U.P., 2026:AHC-LKO:55848-DB: report (Verdictum, 18 August 2026)
- M/s Ultra-Tech Cement Ltd. v. Mast Ram, [2024] 9 S.C.R. 443 : 2024 INSC 709 (Digital Supreme Court Reports)

Shri Law Chambers. Practises before the Allahabad High Court in service and criminal matters; in practice since 1991.
Enrolled with the Bar Council of Uttar Pradesh, 1991 · Advocate-on-Record, Allahabad High Court · Allahabad High Court Bar Association · LL.B., Faculty of Law, University of Allahabad, 1990 · Former standing counsel: Government of India; Zila Panchayat, Kanpur Nagar; Fisheries Department (Matsya Palan Vibhag), Government of Uttar Pradesh